CODE OF
FEDERAL REGULATIONS
TITLE 1--GENERAL
PROVISIONS
CHAPTER
III--ADMINISTRATIVE CONFERENCE OF THE UNITED
STATES
PART
305--RECOMMENDATIONS OF THE ADMINISTRATIVE
CONFERENCE OF THE UNITED STATES
1 C.F.R. s 305.84-1
s 305.84-1 Public
Regulation of Siting of Industrial Development
Projects (Recommendation No. 84-1).
Major industrial
development projects often have significant
environmental effects and require permit approvals
and preparation of environmental reviews by
agencies under legislation such as the National
Environmental Policy Act (NEPA) and the Clean Air
Act. Although governmental permitting and review
processes--aimed at protecting the environment,
reducing safety risks, and assisting the planning
of livable communities--necessarily extend the time
required to complete projects, unnecessary delays
associated with the complexity of lengthy processes
can have serious negative consequences. Project
costs can rise dramatically over initial estimates,
resulting in increased costs to consumers for the
products or services eventually delivered. Project
approval delays have led to pressure to circumvent
environmental laws by means of special legislation
for particular projects or types of projects. The
consuming public can further suffer from process
delay by being deprived for substantial periods of
time--and, in cases of project abandonment caused
by delay, forever--of the benefits of emerging new
technology. The Administrative Conference
[FN1] believes that, when many agencies at
different levels of government must approve a
project proposal, the complexity and uncertainty of
the process can be reduced through an appropriate
degree of interagency coordination and the use of
adequate procedures.
[FN1] Congress
requested that the Administrative Conference (ACUS)
work cooperatively with the Advisory Commission on
Intergovernmental Relations (ACIR) toward resolving
regulatory conflicts and overlap among federal,
state, and local agencies. ACUS and ACIR were
specifically asked to address the issue of
streamlining the permit process based on approaches
that lead to improved intergovernmental
cooperation. Congress was concerned with the
complexity and costs associated with the permit
process in the review of energy and port
development projects. Congress expects ACIR and
ACUS to work together to assess alternative ways to
resolve intergovernmental problems and conflicts in
permitting. In conducting this joint effort, the
agencies have sought and will continue to seek the
input of business, government, and environmental
experts. House Committee on Appropriations, Report
on Treasury, Postal Service, and General Government
Appropriation Bill, 1983, H.R. Doc. No. 854, 97th
Cong., 2nd Sess. 39 (1982). ACIR has cooperated in
the development of this recommendation, but has not
formally adopted the recommendation at this
time.
Interagency
Coordination
Many Federal, state, and
local agencies must review environmentally
sensitive industrial projects. Project developers
need assistance in determining which agencies must
be consulted for project approval, what permits are
required, what applications must be completed, and
what information is need for each application.
Developers' informational needs could be met by a
clearinghouse established at the level of
government closest to initial project review.
When relatively few
agencies must consider a project application,
agreements can be worked out among the agencies to
coordinate agency review or to resolve
jurisdictional or interpretative conflicts. These
agreements can facilitate more timely project
review, reduce overlapping review, decrease
uncertainty, and provide for joint state-federal
agency review of a project.
When many agencies with
different responsibilities, distinct agency
missions, and different governing statutes must
approve a project proposal there is a strong need
for coordination. Selection of a coordinating
agency early in the application process is
desirable to facilitate the permitting process. The
coordinating agency can facilitate the exchange of
information, can encourage more efficient review,
and can reduce the mistrust by scheduling regular
face- to-face meetings among the project developer,
governmental agencies, interest groups, and
residents of the community in which a project is to
be located. The coordinating agency often will have
permitting duties but may be a non- permitting body
such as the Colorado Joint Review Process.
[FN2] To be effective a non-permitting body
must be supported by key government leaders in the
jurisdiction. The coordinating agency may be a body
different from the clearinghouse agency or the lead
agency for environmental review preparation.
[FN2] The Colorado
Joint Review Process (JRP) is an innovative new
approach to coordinating governmental review of
energy projects. Originally part of the Colorado
Department of natural Resources, it is now a wholly
separate body, fully supported by the Governor and
other key state officials. The JRP has no
permitting responsibilities but performs a
coordinating role and operates on a voluntary
basis. A developer must choose to have its project
application accepted into the JRP. The JRP works
with the developer, the public, and all levels of
government to identify affected agencies and permit
processes, to determine what environmental and
other issues must be addressed, to clarify what
information is necessary, and to establish a
decision schedule for all governmental review
processes that must be completed for that project.
The JRP sponsors periodic meetings with all
affected actors and otherwise seeks to ensure a
smoother and more organized review.
Public
Participation
Citizens of the community
in which a project is to be sited have a strong
interest in the project and will seek information
about the project particularly when it has major
environmental effects. Environmental groups and
other members of the public also have similar
interests. Severely limiting legitimate public
participation can unnecessarily increase opposition
to a project and can lead to lawsuits to stop a
project. Facilitating public participation can
reduce fears and concerns, can mitigate the
not-in-my- backyard attitude of a community, and
can lessen public mistrust of the developer and
government. The public can also contribute useful
information to a project. Developers can allay
concerns by sharing information about their project
with the public and can work more effectively by
cooperating with the community in which a project
is to be sited. Public participation at an early
stage of agency review ensures that changes can be
made before substantial developer funds are
committed to a specific project design. Public
participation can be enhanced when meetings or
hearings are held in the project community and when
the agency designates a public advisor to help
citizens understand the process.
Environmental
Review
Under the provisions of
NEPA and similar state legislation, environmental
reviews often must be prepared by agencies prior to
approving a project application. When both federal
and state environmental review statutes apply to a
project application, preparing a joint review can
reduce duplication and overlap. The approach taken
in the regulations of the Council on Environmental
Quality--in which a "lead agency" is designated to
coordinate the preparation of an environmental
impact statement--provides an excellent model
adaptable even when there is no major federal
interest in a project. Early identification of
environmental impacts through the "scoping of
issues" process facilitates statutory compliance
and allows project changes by a developer when they
are least expensive. Identifying commenting
agencies early in the proces ensures that the
concerns of every agency are addressed in the
review. Face- to-face meetings of all participants
in the review process are useful for identifying
impacts, exchanging information, and getting to
know the other participants in the process and
their concerns. The lead agency can ensure a more
timely review process by negotiating a decision
schedule--in which a completion date for each step
of the process is agreed upon--with the project
proponent, other agencies, and representatives of
other identified interested groups. The lead agency
can play a major coordinating role by identifying
other agencies, setting up meetings, organizing the
stages of review preparation, and negotiating
decision schedules for each stage.
Permit Approvals
Developers must file
applications in which they provide information
about their project. Developers and agencies may
disagree as to what information is required and how
much information is adequate for a complete
application. There may also be uncertainty over
procedural and substantive requirements that must
be met. Agencies can assist developers by
specifying in advance the information needed for an
application to be complete and the standards that
must be met for a permit to be approved. The agency
can clarify what is required by holding
pre-application meetings with developers. The
agency can resolve informational, procedural, and
substantive problems by holding post- application
meetings with the developer. Agencies need adequate
information and full cooperation from developers to
make permitting or compliance decisions.
Duplication, overlap, and paperwork can be reduced
if agencies with joint permit responsibilities for
a project adopt common application requirements,
standardized information requirements, and common
procedures such as joint hearings. Sharing of staff
and budgetary resources can make these approaches
easier to implement.
Time Limits for
Decisionmaking
Legitimate concerns are
expressed by developers and others that too much
time is required by agencies to review and permit
major industrial projects. Legislatures have
reacted by passing time limit statutes that mandate
an agency's preparation of an environmental review
or action on a permit application within a set
period of time. [FN3] When setting a time
limit by statute, a legislature must be sensitive
to the agency's needs by allowing in the statute
sufficient time to complete the decision--including
time that may be required for action by other
agencies that have concurrent review
responsibilities, by giving the agency adequate
resources, and by allowing the agency flexibility
to extend the deadline for good cause. Agencies
often have the most knowledge about how long a
particular type of decision can take, and agencies
can specify by regulation an appropriate time
limit. Agency compliance with time limit statutes
can be monitored if the legislature requires
agencies periodically to report their performance
under the statute and to identify any problems
encountered in meeting the time limits.
[FN3] In
Recommendation 78-3 the Conference stated:
"Congress ordinarily should not impose statutory
time limits on an agency's adjudicatory
proceedings. Statutory time limits may be
appropriate, however, when the beneficial effect of
agency adjudication is directly related to its
timeliness, as may be true in certain licensing
cases or in clearance of proposed private activity
where a delayed decision would deprive both the
applicant and the public at large of substantial
benefit." 1 CFR 305.78-3, para. 3. These concerns
for timeliness are particularly pertinent here.
An alternative to mandated
statutory time limits is a requirement that
agencies establish decision schedules which set
deadlines for the completion of specific actions
(e.g., comment periods, drafting of required agency
reports) within each phase of project review. A
decision schedule is desirable because it is
individualized for each project and because it
requires the developer and all responsible agencies
to make commitments to meet the agreed schedule.
Commitment by the developer is crucial since
developers can speed up or slow down development of
a project depending upon internal or external
economic considerations. Also some agencies may not
be sufficiently committed to timeliness; if
agencies are required to agree to a schedule, they
are more likely to make that commitment.
Recommendation
These recommendations are
directed primarily to federal, state, regional, and
local agencies that have permitting and
environmental review responsibilities. In addition,
many of the time limit recommendations are directed
to Congress and state legislatures. To the extent
statutory changes are necessary to implement the
other recommendations, they are also directed to
the appropriate legislative bodies.
[FN4]
[FN4] See
statement regarding joint ACUS--ACIR effort in note
1.
A. Interagency
Coordination
1. Clearinghouses should
be established at the level of government closest
to initial review of a particular project to
provide information to project developers about
applications, agencies to be consulted, and
permitting requirements.
2. Agencies should make
agreements to coordinate review of a particular
project, or to resolve jurisdictional or
interpretive conflicts.
3. A coordinating agency
should be selected to coordinate governmental
review of projects when many agencies are involved.
The coordinating agency may be either a permitting
or a non-permitting agency.
4. The coordinating agency
should schedule regular face-to-face meetings among
developers, agencies, and the public.
5. The Colorado Joint
Review Process approach (note 2, supra) in which a
non- permitting agency coordinates project review
by all agencies is one possibility that should be
considered.
B. Public
Participation [FN5]
[FN5] This part
does not overrule or supersede Recommendation 71-6:
Public Participation in Administrative Proceedings
(1 CFR 305.71-6).
1. In order to facilitate
approval processes, agencies with permitting and
environmental review responsibilities should
solicit and consider the views of public
participants, including citizens of the community
in which a project is to be sited.
2. To make public
participation more meaningful, agencies should
develop procedures such as holding local meetings
or hearings and designating public advisors who can
provide assistance on procedural aspects of agency
proceedings to participants.
3. Agencies should
encourage developers to provide information to the
community about a project application and to be
responsive to legitimate community concerns.
4. Agencies should ensure
that public participation occurs at an early stage
of project review and developer planning so that
changes in project design can be made before
substantial funds are committed to a specific
project design.
C. Environmental
Review
1. When several agencies
are involved in environmental review preparation
for a single project, a lead agency (federal,
state, regional, or local, as appropriate) should
be designated to coordinate the activities. The
approach taken in the regulations of the Council on
Environmental Quality (40 CFR Parts 1500-1508) is
recommended, even when a formal environmental
impact statement is not required. [FN6]
[FN6] The
Conference is not suggesting that an environmental
impact statement be prepared when none is required
by law, but only that, if environmental review is
to involve several agencies, a lead agency be
selected.
2. The lead agency should
identify commenting agencies and should schedule
face-to-face meetings of all participants in the
review process.
3. The lead agency should
utilize the scoping of issues process to identify
environmental impacts early in the review process
before a draft review is prepared.
4. The lead agency should
negotiate decision schedules--setting deadlines for
completion of scoping, draft review preparation and
comments, final review preparation and comments,
and issuance of a review--with the developers, all
affected agencies, and representatives of other
identified interested groups.
5. When appropriate,
agencies should agree to prepare joint
state-federal environmental reviews.
D. Permit
Approvals
1. Whenever feasible
permitting agencies should specify in advance what
informational, procedural, and substantive
requirements will apply to a particular permit
application.
2. Agencies should be
available for pre-application meetings with the
project developer to clarify informational,
procedural, and substantive requirements.
3. Within a short period
of time after the filing of an application,
agencies should determine whether the application
is complete. Agencies should hold post-application
meetings with developers to discuss procedural,
informational, and substantive deficiencies in an
application, and should promptly advise developers
of any deficiencies throughout the pendency of the
permitting process.
4. Agencies should make
clear to developers that the developers must supply
necessary information in an application and that
their cooperation will greatly assist in the
permitting process.
5. Whenever feasible,
agencies with joint permitting responsibility for a
project should be encouraged to reduce duplication
and paperwork by accepting common applications, by
standardizing informational requirements, by using
in one agency proceeding relevant information
developed in the proceeding of another agency, and
by adopting common procedures such as joint
hearings.
E. Time Limits for
Decisionmaking [FN7]
[FN7] See
generally, Recommendation 78-3: Time Limits on
Agency Action (1 CFR 305.78-3), which is consistent
with this part.
1. Agencies should
negotiate a decision schedule with the project
developer, all affected agencies, and
representatives of other identified interested
groups within existing statutory deadlines. The
schedule should set a deadline for the completion
of specific stages of project review. The schedule
should be contained in an agreement in which the
developer and the agencies make a commitment to
meet the deadlines.
2. If a legislature
[FN8] wishes to limit the time available
for a proceeding, it is preferable that the statute
require the agency to fix the time limit by rule,
rather than to specify the time limit in the
statute itself.
[FN8] As used
here, "legislature" includes Congress, as well as
state, regional, and local legislative bodies.
3. A legislatively
mandated time limit should allow an appropriate
amount of time for the type of decision involved,
should specify the consequences of not meeting the
time limit, and should provide the agency with the
option of extending the time limit for good cause
explicitly stated.
4. Legislatures should
provide adequate resources for agencies to meet
time limit requirements and should periodically
review agency compliance with time limits.
[49 FR 29938, July 25,
1984]
Authority: 5 U.S.C.
591-596.
SOURCE: 38 FR 19782, July
23, 1973; 57 FR 61760, 61768, Dec. 29, 1992, unless
otherwise noted.
[Previous
Part] [Next
Part]
|